Bowen Construction, Inc.
Site Prep & Excavation - Commercial & Residential
360-829-6632
Some our recent project include the following:


Some of the projects below have estimated costs ranging from $5,000 to $1,000,000,000. We are also able to accommodate to your time schedule and can work efficiently along side other subcontractors.
Krispy Kreme - Seattle
General Contractor: Wilcox Construction
Estimated cost $325,000
Down spout lines, footing drains, cap break, grease interceptor, storm system, storm filter, water line, prep for sidewalks, curb excavation and grade parking area for asphalt sub grade, street improvements along 1st Ave, Holgate, and Occidental.
USCG D/B Shore Ops. Bldg. - Seattle
General Contractor: Howard S. Wright Const. Estimated cost $500,000 Demo and regrade existing parking area, on site storm, storm filter vault, footing excavation slab prep, sidewalk prep, grade for asphalt, tie in sewer, FDC line, PIV valve, fire line, water main extension, install hydrants, and 3 street tie-ins.
Winterpond - Pierce County
Project Owners: Gene & Sue Hahto
Estimated Cost $1,100,000
30 - lot housing development in Pierce County. Erosion control, 35,000CY pond excavation, 5000LF of storm, asphalt prep for road, county road upgrades, electrical trenching, water main and stubs.
Enterprise Rent-A-Car - Sea Tac
General Contractor: Wilcox Const.
Estimated Cost $750,000
Erosion control, excavate for 154 x 19 x 14 retention vault, export 17,000 CY of unsuitable material, import 15,000 tons of structural backfill, tie-in on Pacific Hwy., water, sewer, storm, building excavation, slab prep, sidewalk prep, curb prep, and retaining walls.
General Contractor: SD Deacon
Estimated Cost $185,000
Street tie in—sewer, water and storm, on site water storage—190LF of 75” x 112” tank, roof drain infiltration system, slab prep, sidewalk prep, grade for asphalt, tie in sewer, FDC line, PIV valve, fire line, footing excavation, and footing drains.

General Contractor: SD Deacon
Estimated Cost $350,000
300 LF 54” storm retention, 4 storm vaults, FDC, fire line, 19’ deep sewer tie-in, building excavation.